January 11, 2005, Vancouver, BC
- Brad Janorschke, General Manager of Homer Electric
Association (“HEA”), and
Bruce Jenkins,
Chief Operating Officer for Northern Dynasty Mines
Inc., a wholly owned subsidiary of Northern Dynasty
Minerals Ltd. (AMEX:NAK; TSXV:NDM), are pleased to
announce a joint initiative to review the
feasibility of a phased power development plan for
the Pebble gold-copper-molybdenum deposit, located
in southwestern Alaska, USA. The Pebble Project is
currently the focus of a comprehensive program of
drilling, engineering and
environmental/socioeconomic work designed to
complete an overall feasibility study and
environmental permit applications in 2005 in
anticipation of a large-scale open pit mining
operation.
HEA and NDM have agreed to jointly assess the
technical, economic, and environmental feasibility
of a phased development approach to ensure the
timely delivery of electrical power to construct and
operate a mine at Pebble. A phased approach
contemplates the efficient start up of a mine, and
the possibility of a subsequent production ramp up
to a milling rate in the order of 200,000 tonnes per
day. The results of this joint review will
contribute to the feasibility study of the Pebble
Project, which is targeted for completion later this
year.
HEA is one of the six prime electric Cooperatives,
or utilities, that service the Alaskan Railbelt
transmission grid. This grid includes Anchorage,
Fairbanks, Matanuska–Susitna, and the Kenai
Peninsula and services about 75% of Alaska’s
population which consumes over 85% of the State’s
electrical power. HEA is a member-owned electric
Cooperative that serves Alaska’s western Kenai
Peninsula. Its beginnings date back to 1945 when
residents in Homer,
Alaska
came together for the purpose of starting a local
electric Cooperative. In 1950, the system was
energized, bringing electricity to 56 members.
Today, the Cooperative consists of approximately
20,000 members and provides electricity to about
28,000 meters in its service area. The Cooperative
supplies power to a mix of heavy industry (an oil
refinery, oil and gas fields in Cook Inlet, a liquid
natural gas production plant and a nitrogen products
plant), towns, rural areas and remote villages over
a territory of 3,166 square miles.
The power development plan which is being reviewed
for the Pebble Project consists of two stages. Stage
One would connect the mine to the Railbelt
electrical grid, via either 210 miles of overland
transmission line, or alternatively, 45 miles of
submarine cable across Cook Inlet, followed by
approximately 70 miles of overland transmission line
to the Pebble property. En route, local villages
and other consumers in proximity to the project area
could likely also be connected to the new
extension. During 2005, HEA and NDM plan to expand
their discussions with local communities to
determine the best approach for optimizing the
supply of power to Pebble and its neighbors in the
region. It is anticipated that HEA will position
itself to provide approximately 100 megawatts of
power to start-up the project. Project start-up
remains subject to completion of the overall
feasibility study, permitting, financing and
detailed engineering.
Stage Two would involve construction of additional
generation facilities by HEA using the best
available technology. The generation capacity would
be optimized to the needs of HEA’s members,
including NDM, as well as to allow for the future
growth of HEA and the remainder of the Railbelt.
Under this new NDM/HEA initiative, the timeline for
the provision of power is consistent with
engineering, permitting and construction
efficiencies. This timeline should also facilitate
a very effective sequence for the potential mine
development. Three mining rates were described in an
independent Preliminary Assessment of the Pebble
Project which was announced in November 2004:
100,000 tpd, 100,000 tpd ramping up to 200,000 tpd
in year 6, and 200,000 tpd. Continuing studies
indicate that the Pebble resource is large enough to
potentially utilize the largest, most cost effective
and efficient grinding equipment currently
available. Consequently, one of the prime
alternatives under investigation is an ultimate
production rate of up to 200,000 tonnes per day (70
million tonnes per year).
A
staged build-up of power availability and mine
production could have numerous benefits. On the
power side, there would be time to optimize
technical details and economic benefits and plan for
growth on the entire Railbelt system. Benefits
would accrue through the ability to plan for grid
expansions and additional power generation in a cost
effective manner that accommodates existing
consumers as well as growing demand from new
consumers. The end result could be a more stable,
efficient system with lower cost electricity
available to all Railbelt customers.
For further information regarding this release
contact:
Joe Gallagher HEA (907) 283 2324 (Public
Relations Coordinator)
Bruce Jenkins NDM (604) 684 6365 (Chief
Operating Officer)
www.northerndynasty.com